Terrain stabilization of the white sugar silo site of Diamant-Zucker KG Könnern

Owing to unstable terrain conditions on the site of the white sugar silo installation of the Könnern sugar factory, two of the three silos started to tilt after being filled for the first time, as did the elevator tower. By a special method, the Soilfrac process, a concrete suspension was pressed into the subsoil under each edifice, which restored both silos and elevator tower to their vertical position.